Queanbeyan Conservation Alliance

Still time to halt the EDE – more petition signatures presented

It’s still not too late to stop the Ellerton Drive Extension (EDE), with construction work yet to commence. So we presented more signatures to the 13 December meeting of Queanbeyan-Palerang … Continue reading

January 18, 2018

Comments closing on draft Integrated Transport Strategy

The long-awaited transport strategy for Queanbeyan-Palerang has been issued for public comment but you don’t have long. True to form, the council issued the strategy and accompanying action plans just … Continue reading

January 18, 2018

Mayor and Deputy Premier confirm EDE failure

The prospect of the $86 million Ellerton Drive Extension (EDE) providing any real relief from heavy vehicle traffic through the Queanbeyan CBD has now been thoroughly discredited – by the … Continue reading

January 17, 2018

Still time to halt the EDE – more petition signatures presented

It’s still not too late to stop the Ellerton Drive Extension (EDE), with construction work yet to commence. So we presented more signatures to the 13 December meeting of Queanbeyan-Palerang … Continue reading

December 13, 2017

Same old lies trotted out as conservative politicians dig in on EDE construction

It was a case of trotting out the same old lies as the three conservative amigos – Mayor Tim Overall, Deputy Premier John Barilaro and ACT Senator Seselja – attended … Continue reading

November 20, 2017

EDE design changed – lighting & median strip scaled back

Key features of the Ellerton Drive Extension (EDE) were changed after the design was exhibited for public comment. The median strip was removed in places and most of the lighting … Continue reading

October 25, 2017

EDE 12 months behind schedule even before work starts

Residents living along the alignment of the Ellerton Drive Extension (EDE) received a letter on 6 October 2017 advising them of early work – three weeks after the public announcement … Continue reading

October 7, 2017 · Leave a comment